Naivasha – Njabini (C67) Road Project

Scope of the Project

  1. The project is located in Nakuru and Nyandarua Counties, South Rift Region of Kenya National Highways Authority (KeNHA).
  2. The main works are located along the 19.9km Kinamba – Githioro (C67) Road which is to be newly constructed.
  3. However, there are additional works under the Contract that covers the rehabilitation of 3.2km Naivasha – C67/A104 Junction, as well as the repair and rehabilitation of the 4.2km section of C67/A104 Junction – Kinamba Road.

 

Description of the Project

The project is funded by Government of Kenya (GoK) – (Development Vote).The Employer is Director General (KeNHA).The contractor being  M/s Victoria Engineering Co.Ltd.

Award date was 30th of December 2019 and date of Commencement being 19th March, 2020.Construction Period of 30 Months and date of Completion being 18th of September, 2022.