On-Going Roads Projects

No Project Name/Activity Region/County Funding Length  Base FY 2017/2018


       MODEL  (Lane KM)   KM Achievement Lane (Km)
Q1 Q2 Q3 Q4

Acc. Lane(Km)

Physical

Progress

 1 Loruk – Barpelo (B17) Baringo/Elgeyo Marakwet   GoK 132  82         82   89.0%
2 Nuno-Modogashe (A13) Garissa  BADEA/KUWAIT/GoK  270 131 15       146 58.0% 
 3  Eldoret Bypass Uasin Gishu   AfDB/GoK 64         4.0%
4 Construction of Kibwezi - Mutomo - Kitui Makueni/ Kitui Exim/GoK  384  31       39 32.0% 
5 Mombasa – Mariakani Contract 1: Mombasa – Kwa Jomvu Rd (A109) Mombasa   AfDB/GoK  80 4.608 0       4.608  30.2%
6 Upgrading of Kalobeiyei River - Nadapal Turkana   IDA/ GoK 176   0 2       2 3.1% 
7 Upgrading of Lokitaung Junction -  Kalobeiyei River Turkana IDA/ GoK  160  3       3 2.5%
8 Upgrading of Lodwar - Lokitaung Junction Turkana  IDA/ GoK   160 4       4 12.6% 
9 Upgrading of Loichangamatak - Lodwar Turkana   IDA/ GoK  100       2 8.6% 
 10 Kisii – Ahero –Isebania (A1) Lot 1: Isebania - Kisii Kisii/Migori AfDB/GoK  368  0 9       9 8.7% 
11 Kisii – Ahero –Isebania (A1) Lot 2: Kisii - Ahero Kisii/Kisumu AfDB/GoK 384  0.12 10       10.12 8.3% 
12 Kitale – Endebes - Suam Busia/Bungoma AfDB/GoK   90 2       2 4.0% 
13 Chiakariga – Meru (C92) Meru  GoK 110 40.85  4       44.85 70.0% 
 14 OljoOrok - Dundori (B20) Nyandarua  GoK  70  18         18 95.0% 
 15 Garsen – Lamu – Witu Lamu  GoK  270  4       4 10.0% 
 16 Uplands - Githunguri Kiambu GoK  94   0       10.0% 
17 Nyaru - Iten Elgeyo Marakwet GoK  64 0 4       4 25.8%
18 Ugunja-Nyadorera-Ruambwa Siaya GoK 26.7 0 0       0 21.7%
19 Mau Narok-Kisiriri (B18) Narok GoK  34 0       0 11.8% 
20 Busia - Malaba Busia GoK  28 0 5       5 43.5%
21 Narok - Sekenani Kajiado  GoK  164  20.4 16       36.4 55.0% 
22 Kisumu - Kakamega Kisumu/Kakamega IDA/ GoK   152  126 3       129  97.7% 
23 Kakamega - Kaburengu (Webuye) New Kakamega  IDA/ GoK   80 28.33 5       33.33 61.1% 
24 Kisumu Boys - Mamboleo Kisumu  IDA/ GoK   18.4 6.89 2       8.89  76.8%
25 James Gishuru- Rironi Nairobi/Kiambu IDA/ GoK 156 5.8 4       9.8 10.0%
26 Dualling of Athi River - Machakos Turnoff Machakos  IDA/ GoK   40  0 2       2 43.7% 
27 Construction of Interchange at Kericho Jn (B1/C23) Kericho  IDA/ GoK  N/A  19% 16%        34.59%  35.0% 
28 Construction of Interchange at Ahero Jn (A1/B1) Kisumu  IDA/ GoK  N/A  15%  12%        27.43% 27.0% 
29 Construction of 3 interchanges at Nakuru Nakuru  IDA/ GoK  N/A  94% 4.00%        98.0%  98.0% 

LATEST UPDATES



Who's Online

We have 15 guests and no members online

Let's go social

fb1   twitter1   1478812163 social square google plus1   1478812150 social youtube square1   1478812020 Instagram   1478812106 social linkedin square1  

News letter

This module can not work without the AcyMailing Component